Project: MattJ   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Matt Jakus   -  
Project:   The Airplane Factory - Sling TSi   -   VIEW REPORTS
Total Hours:1190.7
Start/Last Date:Dec 01, 2019 - Jan 29, 2023
Engine:Rotax 915is
Panel:Garmin 3X
 
Friendly URL: https://eaabuilderslog.org?s=MattJ

Home or Last Project Picture

Mar 23, 2021     Install the avionics & antenna cables - (15 hours)       Category: Avionics
With rack installed the avionics came next. The main wire bundles were pre-made and run through the aircraft. The comm and GPS antenna were then run. I added a tiered support through the center channel to support various items.. AOA, Pitot, and static on one level. Fuel lines bottom level, Wire bundles and antenna mid level going to the lower levels.

I had already wired the connectors to the landing/taxi, position/strobe lights, trim motors and servos. These were happily found to be of the correct length with only one connector miss-pinned. The wings were rolled around to check panel switches and pitot heat...I fabricated battery cables and ran power to the relays and mounted an aircraft ground on the firewall. A final check of the Garmin systems with software updates was completed

It was nice to have help in this important task


 